Stek has successfully represented grid operator Liander in a dispute before the Authority for Consumers and Markets (ACM) pursuant to a complaint submitted by Notos Wind. Notos Wind argued that it has the right to a connection of more than 2 MVA to the local distribution grid. Liander has explained that connections of more than 2 MVA to the Liander grid have to be connected to the nearest substation, not the local distribution grid. By decision of 24 January 2018 ACM has rejected the complaint of Notos Wind.
Click here for the decision in Dutch.